DART Nearing Completion of New Silver Line, Preparing to Open Regional Rail Project

DART Nearing Completion of New Silver Line, Preparing to Open Regional Rail Project

DALLAS — Dallas Area Rapid Transit (DART) is nearing completion of the new Silver Line and preparing to open the 26-mile regional rail project to passengers for revenue service between the end of the year and early 2026. 

According to DART officials, the new Silver Line is about 85% complete with construction and, once in operation, will connect passengers from East Plano to DFW Airportโ€™s Terminal B. The project crosses seven citiesโ€”Addison, Carrollton, Coppell, Dallas, Grapevine, Plano, and Richardsonโ€”across three counties and is adding 10 new transit stations to the existing DART network, a news release stated.ย ย 

Vehicle Testing Coming to New Areas 

With the project covering such a large area, DART and its design-build contractor, Archer Western Herzog (AWH), separated the Silver Line into three segments during construction. Segment C, which runs between Plano and Richardson, was primarily completed in late 2024, allowing DART to begin testing vehicles in the area in late 2024. 

“Vehicle test runs are set to begin by the end of January in Segment A, which runs from DFW Airport to Carrollton, allowing DART to test the trains, track, signals and crossings to ensure a safe a reliable ride while also getting engineers comfortable with the new trip routes,” the release stated. “Specific testing times have not been set, but DART is working to coordinate with cities and school districts to ensure the public is aware of trains operating on the lines with more frequency.”

Testing will continue later this year is supposed to connect Carrollton and Addison to Segment B, which includes the North Dallas area. This segment reportedly required some of the most extensive construction and the closure of Hillcrest Road in February 2024. End-to-end testing of the entire Silver Line track is scheduled to begin this summer once major construction is completed in each segment. 

Construction Milestones coming for Carrollton, Plano, Richardson 

DART also celebrated the groundbreaking of its new Equipment Maintenance Facility in October and work on the 40,000-square-foot facility in Planoโ€™s technology corridor is progressing steadily. The facility is being constructed a few hundred feet from the Silver Lineโ€™s new Shiloh Road Station directly behind a 20,000 square-foot office building that DART purchased to serve as the home to Silver Lineโ€™s administrative and operations team. 

Carrollton will also see changes earlier this year, with DART constructing a new elevator tower to provide passengers a seamless connection between the new Silver Line station and the Green Lineโ€™s aerial platform at the Downtown Carrollton Station. Weather recently delayed the installation of the tower, but DART plans to follow through on that construction as soon as possible, officials said.

Denton County Transit Authority announced plans to extend its service to Downtown Carrollton in the future. Once in place, Silver Line passengers will have transit access to Downtown Denton via DCTAโ€™s A-train in Carrollton and Downtown Fort Worth via Trinity Metroโ€™s TEXRail at the DFW Airport North Station in Grapevine. 

The CityLine development in Richardson will also see changes once the Silver Line is complete.

“The bridge, which crosses over US-75 and spans almost a mile in length, leads the Silver Line into the developmentโ€™s new station will be getting aesthetic arches to give it a unique and vibrant look. DART anticipates adding the arches to the bridge in 2026,” the release stated.

For more information about the Silver Line visit www.DART.org/silverline.

Source: Dallas Area Rapid Transit (DART) 

Similar Posts

  • NEW ENERGY AND BIG PLANS FOR BEAUMONT, TEXAS

    FacebookXRedditPinterestEmailLinkedInWhatsApp Beaumont, Texas, is home to one of the countryโ€™s most sophisticated industrial operations, supporting thousands of jobs and creating new products every day. And with ExxonMobilโ€™sย latest expansion of a new high-performance polyethylene line, the Beaumont story continues to grow. ExxonMobilโ€™s polyethylene plant in Beaumont will increase production capacity by 65 percent, or 650,000 tons,…

  • OSHA NEWS: U.S. Department of Labor Announces Annual Adjustments to OSHA Civil Penalties

    FacebookXRedditPinterestEmailLinkedInWhatsApp By Subcontractors USA News Provider The U.S. Department of Labor has announced adjustments to Occupational Safety and Health Administration (OSHA) civil penalty amounts based on cost-of-living adjustments for 2021. In 2015, Congress passed the Federal Civil Penalties Inflation Adjustment Act Improvements Act to advance the effectiveness of civil monetary penalties and to maintain their…

  • The Data Dilemma for Subcontractors: How to Choose a Monthly Plan

    FacebookXRedditPinterestEmailLinkedInWhatsApp By Subcontractors USA News Provider How much data do you really need on your monthly cellular plan? Buy too much and you’re simply wasting money. Buy too little and you could end up socked with overage fees, or find your data speeds slowed significantly.ย  Though you need wireless service to conduct business, you also…

  • ExxonMobil to invest up to $100 million on lower-emissions R&D with U.S. National Labs

    FacebookXRedditPinterestEmailLinkedInWhatsApp ExxonMobil said today it will invest up to $100 million over 10 years to research and develop advanced lower-emissions technologies with the U.S. Department of Energyโ€™s National Renewable Energy Laboratory and National Energy Technology Laboratory. ExxonMobil to invest up to $100 million on lower-emissions R&D with U.S. National Labs Ten-year agreement with National Renewable…

  • House Bill 4342 Moves Ahead

    FacebookXRedditPinterestEmailLinkedInWhatsApp Following an April 16 hearing,ย House Bill 4342ย was approved by the House Public Education Committee the next day. HB 4342 now advances with the committeeโ€™s full support. HB 4342 would add a licensed architect to theย Texas School Safety Center (TxSSC)ย Board of Directors. TxSSC is the official, university-supported research center at Texas State whose mission is…

  • Officials Break Ground on TxDOTโ€™S Clear Lanes Project

    FacebookXRedditPinterestEmailLinkedInWhatsApp TxDOT to Rebuild/Widen I-35E/US 67 Corridor That First Opened in 1950s DALLAS โ€” Texas Department of Transportation officials and state and local leaders kicked off construction on The Southern Gateway corridor Wednesday, marking the beginning of a four-year effort to rebuild and widen I-35E and US Highway 67 in southern Dallas County. Texas Transportation…