Dallas City Council Approves DART D2 Subway Resolution

Train

By Subcontractors USA News Provider

Recently, the Dallas City Council unanimously approved a resolution supporting the Dallas Area Rapid Transit (DART) D2 Subway project, a second light rail line through downtown Dallas that will extend from Victory Park to Deep Ellum. The resolution includes a commitment to continue to work towards addressing community concerns on the east end of the alignment. 

“The DART D2 Subway project is an important regional project,” explained Paul N. Wageman, chair of the DART Board of Directors. “The second light rail alignment through downtown Dallas is a long-term investment in mass transit to support both the city’s and the region’s goals of a more walkable, transit-oriented and sustainable region. The DART Board appreciates the Dallas City Council’s continued support of this transportation initiative.” 

The DFW area continues to experience unprecedented growth, with new businesses and residents moving to the area every day. The primary purpose of the D2 Subway project is to add long-term passenger carrying capacity to the DART light rail system and provide operational flexibility and added reliability – especially important for the thousands of riders that use the DART system every day to get to work, services, and school. 

DART began planning for the D2 Subway project in 2007 and the 30% level of preliminary design was completed in October of 2020. DART will continue to work with the Federal Transit Administration (FTA) to request re-entry into the Capital Investment Grant program engineering phase as a core capacity project.  The first step in this process will be for the FTA to issue the Final Environmental Impact Statement/Record of Decision along with the 30% design package. Public, agency and stakeholder involvement will continue to be integral to the process. 

“The DART D2 Subway project demonstrates a commitment to strengthening the DART system and creating a more transit-oriented and accessible network for the benefit of our riders and the residents of North Texas,” said Wageman. “The next several months will be focused on continuing the collaborative, multi-agency effort among DART, the City of Dallas, the North Central Texas Council of Governments and TxDOT to evaluate any proposed refinements, enhancements, and/or modifications to the east end of the corridor in coordination with stakeholders.”  

More information about the DART D2 Subway project can be found at www.dart.org/D2. 

Source: Dallas Area Rapid Transit (DART)

Similar Posts

  • San Antonio City Council Approves Creation of Multimodal Transportation Commission

    FacebookXRedditPinterestEmailLinkedInWhatsApp In a major step toward building a safer, more connected transportation network, the San Antonio City Council passed an ordinance creating the Multimodal Transportation Commission. This new advisory body will provide input and recommendations on policies affecting not only drivers, but pedestrians, cyclists, and transit users. The commission’s creation follows a series of policy…

  • Why it’s time to take your safety enrollments and orientations online

    FacebookXRedditPinterestEmailLinkedInWhatsApp OSHA has placed a heavy burden on construction operations to adhere to stringent safety regulations. All workplaces must conform to the agencies guidelines and standards. Proper tool usage, safety equipment, training, and hazard notices all seem like common sense practices. But many worker duties can evolve quickly and pulling a safety trainer to update…

  • Ensuring Your Home Heating Equipment Operates Efficiently All Season

    FacebookXRedditPinterestEmailLinkedInWhatsApp By Subcontractors USA News Provider  Want a snafu-free season of home heating? Better installation and quality service mean a longer life for your heating and cooling equipment, as well as increased energy efficiency and reduced energy bills. Not only that, regular service checks may actually detect problems before you notice them, and catching them…

  • 11 TIPS TO PREPARE TO PULL A BUILDING PERMIT DURING HURRICANE SEASON

    FacebookXRedditPinterestEmailLinkedInWhatsApp Hurricane season officially kicked off along the Texas Gulf Coast area on June 1,2020 and runs through November 2020.  And while this region has experienced many thunderstorms, major floods and hurricanes over the years that wreaked havoc, Hurricane Harvey, and its aftermath in 2017, was a wake-up call still fresh in our memory that…

  • Prepare for Automated Construction Fleet Vehicles

    FacebookXRedditPinterestEmailLinkedInWhatsApp Technology is changing at a rapid pace, and the construction industry is not without its opportunities to automate processes and adopt the latest industry advancements. The increased availability of partially automated vehicles is the latest example of how companies everywhere can improve the efficiency and safety of their fleets. But that doesn’t mean contractors…