Houston Airports News: Crunch Time – Heavy Machinery Characterizes Ongoing Construction as Terminal Modernization Program Advances

iStock 104294095

By Subcontractors USA News Provider

If you’ve  departed or  arrived at  George Bush Intercontinental Airport recently, you have likely noticed the  roadway  construction  that  is paving the way for a new  elite and  technologically advanced international terminal,  which is one  of two  main  projects  under the IAH Terminal Redevelopment Program, ITRP.

Roadway and utility construction on North Terminal Road at Bush Airport has necessitated the temporary reduction in  the number of lanes leading to Terminals C, D and E. Traffic congestion is likely during peak times for passengers departing from  these terminals.  Passengers are encouraged to  build an extra hour  into their trip time and – very important – follow the signage.  

“During this  time of  tremendous  growth and expansion, communication with  passengers, stakeholders and the community is  critical,”  Houston Airports  Director of Communications and Public Relations  Foti Kallergis  said.  “This expansion puts our intentions on full display as we create facilities for which the airport, the city and the country can truly be proud. We want everyone to know that this temporary inconvenience will yield great dividends for our city.”  

TERMINAL CONSTRUCTION UPDATE:  

The Terminal D/E Parking Garage is now permanently closed, making way for construction of the incredible new international terminal arrivals and departures hall. The new hall  will  vastly  improve the experience for passengers traveling to and from international destinations and will create jobs for Houstonians.  

Additional ITRP construction  activities  includes  the ongoing  Radio Intermediate Distribution Frame, RIDF, Relocation Project which will enable and improve the airport’s extensive communications network.   

These lane closures and  temporary inconveniences to some passengers are being minimized as much as possible in making way for the  further  modernization of  Bush Airport, the highest-ranked U.S. airport and the second-best airport in North America at the 2020 Skytrax World Airport Awards.  

In June, construction included: 

  • installation of a new Centerpoint Energy electrical duct bank to serve the ITRP projects; 
  • foundations started for the temporary sterile corridor adjacent to existing Terminal D; 
  • utility work continues for the new D West Pier and; 
  • new waterline began installation on North Terminal Road for service capacity expansion in the central terminal area. 

In July, construction entails: 

  • continuation of roadway improvements on North Terminal Road; 
  • CenterPoint continues with the installation of an electrical duct bank on North Terminal Road; 
  • foundation work begins for the new D West terminal and; 
  • selective demolition begins at night for the existing Terminal D/E Garage. 

The overall ITRP scope is comprised of two large projects making up the International Terminal Complex and enabling projects. The International Terminal Complex is comprised of:   

  • The International Terminal – North Concourse Project.  This is comprised of two parts – the refurbishment and re-life of the existing Terminal D facility;  and the demolition and construction of the New Terminal D West Concourse.  
  • The International Terminal – Central Processor (ICP) and Federal Inspection Services (FIS) Project.  This is comprised of the demolition of the existing Terminal D-E Garage, roadway modifications and construction of the new International Central Processor (ICP) building. In addition, there will be modifications to the existing Federal Inspection Services (FIS) building.  

The Program’s careful  planning includes safeguarding for  even  further  expansion of  the international terminal  as passenger and airline traffic grows beyond the record levels attained in 2019, pre-pandemic.  

For more information, please visit https://www.fly2houston.com/.

Source: Houston Airports

Similar Posts

  • Bexar County Supplier Registration Opens Government Contracting Opportunities

    Bexar County Supplier Registration is an important first step for businesses looking to compete for government contracts and procurement opportunities in South Texas. Through the county’s online Supplier Portal, vendors can create profiles, select commodity codes and receive notifications about upcoming bids and solicitations across multiple county departments. Whether serving the construction, technology, professional services,…

  • 10 THINGS YOU MIGHT NOT KNOW ABOUT NATURAL GAS

    Natural gas – it heats our homes, powers our appliances, generates electricity and can even fuel vehicles. This versatile and abundant resource is helping to drive a manufacturing renaissance across America and contributing to emissions reductions all over the world. Though natural gas is in the news quite a bit, many people only associate it with home…

  • South Texas county backs $1.8B steel mill project with new reinvestment zone

    Commissioners in San Patricio County, Texas, took the first step last week in securing a $1.8 billion Steel Dynamics mill for the Corpus Christi area by voting unanimously to create a reinvestment zone that includes the approximately 2,500-acre piece of land on which the company would build the plant, according to The Corpus Christi Caller…

  • Tips for a Successful Young Professionals Event

    Subcontractors USA News Provider So you know you want to attract, retain and add value to the young professionals in our industry, but where do you begin? How do you get them interested and engaged? Young Professionals (YP) is a versatile term. A Young Professional can be: someone right out of high school or college…

  • Survey Says: Here Are the Top Three Building Permitting Questions Most Often Asked

    By Helen Callier, Contributing Writer In a construction market that is red hot or one that seems to be cooling, architects, contractors, and project owners are all focused on obtaining building permits fast, starting construction in a timely manner and obtaining a Certificate of Occupancy to open doors for business.  At this point, the project…