Texas Highway Projects Update: TxDOT Progress Across the State

Texas Highway Projects Update TxDOT Progress Across the State

TxDOT Progress Across the State continued in December as the Texas Department of Transportation advanced major infrastructure, safety, and flood recovery projects benefiting communities throughout Texas. From transformative urban highway redesigns in Austin and San Antonio to safety and capacity improvements in North Texas and critical flood repair work in West Texas, TxDOT made significant strides on projects that will improve mobility, safety, and connectivity statewide.

Austin: Prep work underway for historic I-35 redesign

TxDOT’s work on the I-35 Capital Express Central project – the first major redesign of the corridor since 1974 – is well underway. Crews are reconstructing the MLK bridge, advancing work on the Lady Bird Lake segment and building the critical drainage infrastructure needed to support the lowering of the mainlanes between Holly Street and Airport Boulevard.

The project includes 6.5 miles of massive, 22-foot-diameter drainage tunnels, access shafts and a pump station to manage stormwater before excavation begins. Two tunnel boring machines are scheduled to arrive from Germany this year. Once complete in 2033, the project is expected to significantly improve mobility, safety and flood resilience in Austin.

Texas Highway Projects Update TxDOT Progress Across the State 2

North Texas & Panhandle: Safety projects continue in Amarillo District

TxDOT’s Amarillo District reported steady progress on five major safety and capacity projects, including:

  • Widening I-27 between Amarillo and Canyon to six lanes
  • Intersection and turn-lane improvements on State Loop 335
  • Upgraded lighting and drainage at FM 1061 and FM 2590
  • Safety enhancements on Business I-40, including shared-use paths and median barriers

Collectively valued at hundreds of millions of dollars, the projects are aimed at improving safety, supporting growth and reducing crashes across the region.

West Texas: US 67 reopening in San Angelo

In San Angelo, drivers received welcome news as repairs on US67/Houston Harte Expressway neared completion following flood damage caused by historic July rainfall. TxDOT replaced metal pipe culverts—installed in the 1980s—with modern concrete box culverts.

The Loop, closed since late September between Bell Street and North Oakes, is now fully reopen.

San Antonio: Expansion begins on U.S. 90

December marked a major milestone in San Antonio as TxDOT officially began construction on the $473 million U.S. 90 Expansion Project in west Bexar County. The project will widen the highway from four to six lanes, add continuous frontage roads, construct a new flyover ramp to Loop 1604 and build multiple turnaround bridges and upgraded intersections.

Phase I, from Loop 410 to Loop 1604, is underway and expected to finish by 2030. Phase II, extending to SH 211, is expected to begin in 2027.

Bexar County: FM 1518 expansion reaches key milestones

Another major San Antonio-area project—the FM 1518 expansion—continued to move forward in December. Crews completed portions of new lanes, shared-use paths and utility upgrades in Schertz, with bridge widening at Woman Hollering Creek scheduled to finish by year’s end.

The $72.78 million project will ultimately reconstruct 5.6 miles of FM 1518 with wider lanes, a raised median, sidewalks and shared-use paths, improving safety and connectivity through 2028.

With many projects continuing into 2026, TxDOT continues to work to improve safety and connectivity throughout the state.

Summary

TxDOT made significant progress on major transportation projects across Texas in December, including highway redesigns, safety improvements, and flood recovery efforts. From Austin’s I-35 Capital Express project to expansions in San Antonio, North Texas, and West Texas, these initiatives aim to improve mobility, safety, and connectivity for communities statewide.

Source: txdot.gov

Similar Posts

  • Shining the Spotlight on The American Institute of Architecture Students (AIAS)

    FacebookXRedditPinterestEmailLinkedInWhatsApp By Subcontractors USA News Provider The American Institute of Architecture Students (AIAS) is an independent, nonprofit, student-run organization dedicated to providing unmatched progressive programs, information, and resources on issues critical to architecture and the experience of education. The AIAS aims to promote excellence in architectural education, training, and practice; to foster an appreciation of…

  • Texas high-speed train named top global infrastructure project

    FacebookXRedditPinterestEmailLinkedInWhatsApp The Texas high-speed train has been named among the top global infrastructure projects by CG/LA, a national infrastructure advocacy group, in its 2019 Strategic 100 Global Infrastructure Report. Designed to identify projects with the most potential opportunity in the upcoming year, the CG/LA reports select projects with widespread benefits and strategic importance in 30…

  • Port Houston Restoration and Upgrade Project at Barbours Cut Terminal

    FacebookXRedditPinterestEmailLinkedInWhatsApp By Subcontractors USA News Provider Port Houston has obtained an infrastructure grant for the rehabilitation of 2,667 feet of Wharves along the channel and the reconstruction of 87.5 acres of the container yard at the Barbours Cut Container Terminal facility. The work will be performed between July 2022 through September 2027. The project will…

  • CenterPoint Energy NEWS

    FacebookXRedditPinterestEmailLinkedInWhatsApp CenterPoint Energy Announces Outlook Revision To Stable by Moody’s By Subcontractors USA News Provider CenterPoint Energy, Inc. (NYSE: CNP), recently announced that Moody’s Investors Service (“Moody’s”) changed the company’s rating outlook from Negative to Stable and affirmed the company’s Baa2 senior unsecured rating and Prime–2 short–term rating for commercial paper. “Moody’s revision is an…

  • Industry Day 2025: Houston Airports Lays Foundation for Future Growth

    FacebookXRedditPinterestEmailLinkedInWhatsApp Houston Airports welcomed hundreds of industry leaders, contractors, small business owners, and innovators to its annual Industry Day event on Monday, June 9, providing a transparent look at more than a dozen upcoming infrastructure projects scheduled between July 2025 and June 2026. Held at the Humble Civic Center, the standing-room-only event connected decision-makers with potential partners…

  • Capital Metro to Open Vehicle Capacity as Community Reaches Stage 2 Milestone

    FacebookXRedditPinterestEmailLinkedInWhatsApp By Subcontractors USA News Provider Beginning last month, Capital Metro opened all vehicles to full capacity, with the exception of Metro Access, as their community enters Stage 2 COVID-19. The agency is encouraged to see the community reach this milestone and looks forward to continuing to welcome customers back on all services. Customers are…