DFW Airport Completes Runway Rehabilitation Project Ahead of Schedule

DFW Runway 1 Team on Runway

Dallas Fort Worth International Airport (DFW) announced on Friday, October 11 the completion of a major rehabilitation of Runway 17R/35L, one of the largest of the airport’s seven runways, ahead of schedule.

Due to the project’s innovative phasing approach, Runway 17R/35L reopened in a shortened configuration in May and opened in the full operational configuration, a news release said.

“This innovative approach was achieved through strong partnership with the Federal Aviation Administration and American Airlines, which allowed crews to continue working on the full length of the runway while airline partners were able to have beneficial use of the shortened runway during the airport’s record-breaking summer travel season,” the release said.

The undertaking of Runway 17R/35L, which is 13,400 feet long by 200 feet wide, reportedly took more than 350,000 work hours and was achieved with no recordable safety accidents. Work included a complete reconstruction of the runway with a high-density asphalt overlay, and new and improved drainage, lighting, signage and deicing infrastructure.

2024 10 Fact Sheet Runway 17R FINAL
DFW Airport Completes Runway Rehabilitation Project Ahead of Schedule (Photo Credit: DFW Airport)

The project also included several other initiatives, including the replacement of more than 2,700 runway lights to energy-efficient LED fixtures, and the recycling of more than 300,000 cubic yards of reclaimed concrete that was reused in the runway project, in addition to other construction projects at the airport.

“Today marks the successful completion of the largest runway rehabilitation in our airport’s history, which was achieved ahead of schedule and with no recordable safety accidents thanks to our focus on delivering a safe and efficient project,” said Mohamed Charkas, Executive Vice President of Infrastructure and Development at DFW. “This achievement reflects the dedication and collaboration of all our partners and returns one of our busiest runways back into service ahead of the winter travel season.”

DFW was awarded a $45 million Airport Infrastructure Grant under the Bipartisan Infrastructure Law by the U.S. Department of Transportation’s Federal Aviation Administration to assist in funding the investment. The rehabilitation project was completed by Austin Bridge and Road with design by AtkinsRéalis.

The runway project is a part of the airport’s historic nearly $9 billion capital improvement plan, called DFW Forward, which includes major upgrades, expansions and new facilities across the airport’s airfield, terminals and roadways. 

Source: Dallas Fort Worth International Airport

Similar Posts

  • When Will Workers Get a Break?

    FacebookXRedditPinterestEmailLinkedInWhatsApp By Julianne Malveaux, NNPA Newswire Contributor Now that the impeachment trial of the 45th President is over, perhaps our legislators can turn their attention to working people, or more accurately, those who used to work and are not now working. There were 18 million unemployment insurance claims now than a year ago, and nearly…

  • Record-Setting Year for Port Houston

    FacebookXRedditPinterestEmailLinkedInWhatsApp HOUSTON–(BUSINESS WIRE)– Port Houston business has grown consistently and solidly across all business lines, including achieving record-breaking performances and milestones in 2017. Highlights of the record-setting business and operational results for 2017 were announced today during the Port Commission of the Port of Houston Authority first meeting of the year. “We are again on…

  • A passion for empowering women

    FacebookXRedditPinterestEmailLinkedInWhatsApp The empowerment of women in business is a passion that Brenda Erickson has carried throughout a career that has spanned more than three decades. That passion recently earned her recognition as one of the Top 30 Influential Women in Houston. Brenda has mentored more than 100 colleagues through their careers at ConocoPhillips. Additionally, she…

  • Temperature Screenings Strengthen COVID-19 Safety Procedures for the Construction Industry

    FacebookXRedditPinterestEmailLinkedInWhatsApp By Subcontractors USA News Provider A recent report by the CDC identified over 600,000 COVID-19 cases in Texas and more than six million confirmed cases nationwide.  Therefore, measures to mitigate disease transmission remain critical to slow the spread.  In construction, oil and gas, manufacturing, and other related industries, there are special and unique measures…